It will likely come as no surprise, but there are a particularly large number of new developments in the coming week concerning road work taking place in north central Ohio.
This is a weekly report from ODOT District 3 highlighting road construction projects which are beginning or underway in the multi-county area it serves. What follows are posted projects taking place within Ashland, Crawford, and Richland Counties.
Please stay safe and pay attention to these closures and work taking place during the week beginning on May 29. All outlined work is weather permitting.
All the best for safe travels throughout 2022!
ASHLAND
U.S. Route 30 Reduced Conflict U-Turn – U.S. 30, just west of Township Road 1255, will have single lane closures for intersection improvements. Construction work will improve the intersection of U.S. 30 and SR 603 by installing a reduced conflict U-turn (RCUT).
CONTINUING IMPACTS
- SR 603, north of U.S. 30, is closed for 45 days to complete project work at the intersection. The detour route for northbound motorists is SR 603 to U.S. 30, east on U.S. 30 to SR 511, north on SR 511 to U.S. 42, south on U.S. 42 to SR 603, and reverse for southbound motorists. Estimated completion: Thursday, June 16, 2022
- Note, the re-aligned SR 603 south side will be in its new RCUT configuration. Motorists will have a right-in from U.S. 30 to SR 603 south, and a right-out from SR 603 to U.S. 30 east. There will be NO left-hand turn movements and the median will be closed to traffic.
- Lighting, drainage, erosion control and other miscellaneous project work continues.
- A minimum of one 12-foot lane in each direction will be maintained.
Estimated completion of entire project: August 2022
U.S. Route 250 intersection improvements – U.S. 250 at the SR 89 intersection will have lane closures for an intersection improvement project. The project will improve the intersection sight distance by lowering a crest vertical curve to the west of the intersection and widen the radii at the intersection to better accommodate truck turns.
NEW IMPACTS
- The U.S. 250/SR 89 intersection, between Township Road 1500 and County Road 1302, will close Monday, June 13 for reconstruction work of the intersection. One lane of traffic will be maintained at all times on SR 89.
- The detour route for eastbound traffic on U.S. 250 will be I-71 south to U.S. 30 east back to U.S. 250.
- The detour route for westbound traffic on U.S. 250 will be U.S. 30 west to SR 60 north to U.S. 42 north back to U.S. 250.
CONTINUING IMPACTS
- Crews will be installing temporary pavement and completing ditch work on SR 89.
Estimated completion: September 2022
U.S. Route 250 roundabout – U.S. 250, at the SR 60/Faultless Drive intersection, will have lane closures for a roundabout project. This project will convert a two-way stop-controlled intersection into a single-lane roundabout.
CONTINUING IMPACTS
- Crews will begin installing temporary pavement and completing drainage work.
- The slip ramp for U.S. 250 north will close Friday, May 27 per project plans. There will be no detour.
Estimated completion: September 2022
CRAWFORD
U.S. Route 30 resurfacing – U.S. 30 eastbound and westbound, from SR 602 to just east of SR 61, will have single lane closures for a resurfacing project. Estimated completion: September 2022
State Route 39 culvert replacement – NEW IMPACTS – State Route 39, just north of SR 98, will close Monday, June 6 for a culvert replacement. The detour route for northbound motorists will be SR 39 to SR 98, southwest on SR 98 to SR 602, north on SR 602 to SR 103, east on SR 103 to SR 39, and reverse for southbound motorists. Estimated completion: Friday, June 6, 2022
State Route 598 minor widening – State Route 598 in the city of Galion, from Carter Drive to Brandt Road, will have lane closures for temporary pavement and drainage work.
NEW IMPACTS
- Crews will begin permanent widening of the east side of the roadway. Traffic will be shifted to the west side of the roadway and two lanes of traffic will be maintained.
- Traffic on Brandt Road at the intersection with SR 589 will be maintained on the north side of the roadway.
- Traffic will be maintained in 11’ lanes.
Estimated completion of entire project: October 2022
State Route 602 major reconstruction – NEW IMPACTS – State Route 602, between County Route 330 (Old Lincoln Highway) and SR 96, will close Monday, June 6 for 60 days for full-depth pavement reclamation project. One-way local traffic will be maintained. The detour route for southbound traffic will be SR 602 to SR 96, west on SR 96 to SR 98, south on SR 98 to U.S. 30, east on U.S. 30 to SR 602, and reverse for northbound motorists. Estimated reopening: Friday, August 5, 2022 (Estimated completion of entire project: October 2022)
RICHLAND
U.S. Route 30 major rehabilitation – U.S. 30, from State Route 309 to just east of the 5th Avenue ramps, will have single lane closures for a major rehabilitation project. Traffic will always be maintained.
NEW IMPACTS
- SR 39 under U.S. 30 will NOT have periodic closures this coming week. Work on the overhead beam installation has been postponed until the week of June 13. More details to come.
CONTINUING IMPACTS
- The westbound pattern will consist of maintaining one lane of traffic westbound, from just east of 5th Avenue to SR 13, and two lanes of traffic westbound, from SR 13 to just west of SR 309.
- The eastbound pattern will consist of maintaining one lane of traffic eastbound, from just west of SR 309 to SR 13, and two lanes of traffic eastbound, from SR 13 to just east of 5th Avenue. The traffic along U.S. 30 eastbound will only have access to Trimble Road and SR 13.
- The U.S. 30 eastbound exit ramp to SR 39 is closed. The detour route will be to continue eastbound on U.S. 30 to the SR 13 exit, turn right onto Longview Avenue west to SR 13 north, take the SR 13 entrance ramp to U.S. 30 west, and continue west on U.S. 30 to the exit ramp to SR 39. Estimated reopening: September 2022
- The SR 39 entrance ramp to U.S. 30 eastbound is closed. The detour route will be to continue on SR 39 north to the SR 39 entrance ramp to U.S. 30 west, travel west on U.S. 30 to the Trimble Road exit, turn left on Trimble Road and re-enter onto the Trimble Road entrance ramp to U.S. 30 east. Estimated completion: September 2022
- The U.S. 30 eastbound exit ramp to 5th Avenue is closed. The detour route will be to continue eastbound on U.S. 30 to the Reed Road exit, turn left on Reed Road, travel north on Reed Road to the entrance ramp to U.S. 30 west, travel west on U.S. 30 to the 5th Avenue exit ramp. Estimated completion: September 2022
- The 5th Avenue entrance ramp to U.S. 30 east is closed. The detour route will be to continue north on 5th Avenue to the U.S. 30 westbound entrance ramp, travel on U.S. 30 west to the SR 13 exit, turn left on SR 13 to Longview Avenue, and take the Longview Avenue east entrance ramp to U.S. 30 eastbound. Estimated completion: September 2022
- Both eastbound and westbound traffic will be separated by portable concrete barrier throughout the length of the project. Lane widths will be 11’ throughout the work zone.
Estimated completion of entire project: May 2023
State Route 39 city of Shelby streetscape project – SR 39, SR 96, and SR 61 are a part of the sidewalk installation and streetscape improvements in the city of Shelby.
NEW IMPACTS
- SR 39/96 (Main Street), at the SR 39 (Mansfield Avenue/Broadway Street) intersection, will close for 60 days beginning Monday, June 6. Crews will be installing sidewalks and crosswalks, completing signal improvements, completing streetscape items and drainage system improvements at the intersection. The detour route for eastbound motorists will be SR 61 south to Mickey Road, east on Mickey Road to SR 39, south on SR 39 to U.S. 30, east on U.S. 30 to SR 13, north on SR 13 to SR 96, and reverse for westbound motorists. Estimated completion: Friday, August 5, 2022
- SR 39 (Mansfield Avenue/Broadway Street) will be reduced to one lane of traffic at the SR 96 (Main Street) intersection and will have two-way traffic maintained by a portable traffic signal during the 60 day closure.
CONTINUING IMPACTS
- SR 61 (Gamble Street), at the SR 39/96 (Main Street) intersection, is closed for 60 days. Crews will be installing sidewalks and crosswalks, completing signal improvements, completing streetscape items and drainage system improvements at the intersection. The detour route for southbound motorists will be SR 61 south to State Street, east on State Street to Broadway Street, south on Broadway Street to SR 39, south on SR 39 to Mickey Road, west on Mickey Road to SR 61, and reverse for northbound motorists. Estimated completion: Friday, June 10, 2022
- SR 39/96 (Main Street) will be reduced to one lane of traffic at the SR 61 intersection and will have two-way traffic maintained by a portable traffic signal during the 60-day closure.
Estimated completion for entire project: June 2022
State Route 314 culvert replacement – State Route 314, between Millsboro West Road and Wolf School Road, is closed for a culvert replacement. The detour route for northbound motorists will be SR 314 to SR 97, west/northwest on SR 97 to SR 309, east on SR 309 to SR 314, and reverse for southbound motorists. Estimated completion: Friday, May 27, 2022