By 1812Blockhouse; Ohio Department of Transportation
ODOT District 3 has released its weekly report highlighting road construction projects which are beginning or underway in the multi-county area it serves. What follows are posted projects taking place within Ashland, Crawford, and Richland Counties.
Please stay safe and pay attention to these closures and work taking place during the week beginning on August 1.
U.S. Route 30 resurfacing – U.S. 30, from SR 603 to SR 511, will have lane closures in each direction for a resurfacing project. Estimated completion: August 2021
U.S. 30 Reduced Conflict U-Turn – U.S. 30, between Township Road 405 and County Road 175, will have single lane closures for intersection improvements. Construction work will improve the intersection of U.S. 30 and SR 89 by installing a reduced conflict U-turn (RCUT).
CONTINUING IMPACTS
Estimated completion: October 2021
State Route 302 bridge replacement – State Route 302 over Orange Creek, just east of Township Road 851, is closed for a bridge replacement project. The detour route for westbound motorists will be SR 302 to SR 58, south on SR 58 to SR 511, north on SR 511 to SR 302, and reverse for eastbound motorists. Estimated completion: August 2021
State Route 302 culvert replacement – State Route 302, between County Road 175 and Township Road 63, will close Monday, July 19 for a culvert replacement. The detour route for eastbound motorists will be SR 302 to U.S. 42, north on U.S. 42 to SR 604, east on SR 604 to SR 539, south on SR 539 to SR 302, and reverse for westbound motorists. Estimated completion: Tuesday, August 17, 2021
State Route 19 culvert replacement – NEW IMPACTS – State Route 19, just north of Township Road 257 (Kline Road), will close Monday, August 2 for a culvert replacement. The detour route for northbound motorists is SR 19 to SR 598, north on SR 598 to U.S. 30, west on U.S. 30 to SR 602, south on SR 602 to SR 19, and reverse for southbound motorists. Estimated completion: Friday, August 20, 2021
U.S. Route 30 major rehabilitation – U.S. 30, from State Route 309 to just east of the 5th Avenue ramps, will have single lane closures for a major rehabilitation project. Traffic will always be maintained.
NEW IMPACTS
CONTINUING IMPACTS
Estimated completion of entire project: May 2023
U.S. Route 30 bridge repair – U.S. 30 westbound, under Reed Road, will have the driving lane closed for a bridge repair project. Crews will be repairing the structure on Reed Road over U.S. 30. Estimated completion: July 2021
U.S. Route 30 interchange improvements – U.S. 30 eastbound, at the entrance ramp to I-71 northbound, will have single lane closures for interchange improvements. Crews will be constructing a full-length eastbound deceleration lane at the entrance ramp.
CONTINUING IMPACTS
Estimated completion: September 2021
U.S. Route 42 resurfacing – U.S. 42, from Park Avenue East to Indiana Avenue, will have single lane closures for a resurfacing project. Crews will be performing catch basin reconstruction work along various locations within the project limits. Traffic will be maintained by flaggers. Estimated completion: September 2021
State Route 61 resurfacing – State Route 61, from just south of London West Road to SR 98, will have single lane closures for a smooth-seal resurfacing project. Traffic will be maintained by flaggers. Estimated completion: July 2021
State Route 61 culvert replacement – State Route 61, between Brannon Road and Settlement East Road, is closed for a culvert replacement. The detour route for southbound motorists will be SR 61 to SR 314, south on SR 314 to W. Fourth Street, west on W. Fourth Street to U.S. 30, west on U.S. 30 to SR 61, and reverse for northbound motorists. Estimated completion: Friday, July 23, 2021
State Route 96 resurfacing – State Route 96, from just west of Technology Parkway to the SR 13/SR 96 junction, will have single lane closures for a smooth-seal resurfacing project. Traffic will be maintained by flaggers. Estimated completion: July 2021
State Route 309 resurfacing – State Route 309, from just north of SR 430 to N. Home Road, will have lane closures for a resurfacing project. Traffic will be maintained in 11’ lanes. Estimated completion: October 2021
State Route 603 consecutive culvert replacements – NEW IMPACTS – State Route 603, between Lucas Perrysville Road and Pleasant Valley Road, will close Monday, August 2 for three consecutive culvert replacements. The location of each culvert is as follows: 1) At the SR 603 and Lucas Perrysville Road intersection for approximately two weeks; 2) between Welty Road and Schrack Road for approximately one week; and 3) between Hunter Road and Pleasant Valley Road for approximately one week. The detour route for southbound motorists will be SR 603 to SR 39, east/southeast on SR 39 to SR 95, west on SR 95 to SR 603, and reverse for northbound motorists. Estimated completion: Friday, August 27, 2021
Ohio Department of Transportation, road projects