By 1812Blockhouse; ODOT District 3

1812Blockhouse provides regular weekend reports on road project work being conducted under the auspices of the Ohio Department of Transportation (ODOT) in Ashland, Crawford, and Richland Counties.

Such work is, of course, weather dependent. This past week, ODOT District 3 shared announcements of current and upcoming work in the three county area.

U.S. 42 & State Route 302 intersection improvement

NEW IMPACTS

  • The U.S. 42/SR 302 intersection will close Monday, April 22 to begin construction on the new roundabout.
  • This is phase one of the project and will approximately last from April 2024 till June 2024.
  • The detour route will be SR 302 west to SR 301 north to U.S. 224 west to SR 58 south to SR 302, and reverse.
  • Access will be maintained for residents only. The SR 302 eastbound direction at each intersection will be closed to traffic, so all residents will need to enter the zone from the westbound side.

Estimated completion: October 2024


State Route 89 & State Route 302 intersection improvement

NEW IMPACTS

  • The SR 89/SR 302 intersection will close Monday, April 22 to begin construction on the new roundabout.
  • This is phase one of the project and will approximately last from April 2024 till June 2024.
  • The detour route will be SR 302 west to SR 301 north to U.S. 224 west to SR 58 south to SR 302, and reverse.
  • Access will be maintained for residents only. The SR 302 eastbound direction at each intersection will be closed to traffic, so all residents will need to enter the zone from the westbound side.

Estimated completion: October 2024

U.S. Route 30 culvert preservation

U.S. 30, from Crawford Wyandot Road to Old Lincoln Highway, will be reduced to one lane in each direction for a culvert maintenance project. One 12-foot lane of traffic will be maintained with drums and concrete barrier wall. Estimated completion: August 2024

State Route 13 bridge repairs

State Route 13 (N Main Street) in the city of Mansfield, between Olive Street and N Diamond Street, is closed for a bridge repair project. Traffic will be detoured from SR 13 (N Main Street) to E 6th Street to N Diamond Street, and reverse. Estimated completion: Thursday, May 9, 2024


State Route 61 culvert replacement

State Route 61, between Opdyke Road and Bucyrus Street (SR 98), is closed for a culvert replacement. The detour route will be SR 61 north to SR 39 west to SR 598 north to SR 98 north, back to SR 61, and reverse for southbound motorists. Estimated completion: Wednesday, May 8, 2024


State Route 95 culvert replacement

NEW IMPACTS – State Route 95, between Divelbiss Road and Armstrong Road will close Monday, April 22 for a culvert replacement. The detour route will be SR 95 west to SR 97 west to SR 13 south to SR 95, and reverse. Estimated completion: Friday, April 26, 2024


State Route 96 bridge replacement

NEW IMPACTS – State Route 96, between SR 603 and SR 545, will close Monday, April 22 for 120 days for a bridge replacement project. The detour route will be SR 96 west to SR 545 south to SR 603 north to SR 96, and reverse. Estimated completion: Tuesday, August 20, 2024

Send us your news — of an announcement, event,
club news, fundraiser – whatever! It’s easy to do online.

Become a 1812Blockhouse Newsroom Member, support independent media in Richland County, and get access to the new Super Richland! Details here.
You May Also Like

Updates From Avita Health System

By 1812Blockhouse Two updates from the folks at Avita Health System: Reduced…

Socks For Seniors Goal Bigger Than Before

The Ohio District 5 Area Agency on Aging, We ACT, and Richland…

Escape From Shawshank Bike Tour

By 1812Blockhouse After a one year hiatus due to the COVID pandemic,…

Trimble Road To Reopen; Project Continues

On Thursday, June 29 at 6:00 a.m., Trimble Road will be opened…