Section of Oak Street Closed Until Friday; Here Are Details

21 Aug , 2019  

Due to water main repairs, a section of the following road has been closed while work is being completed:

Oak Street from East Second Street to Bushnell Street

The road is expected to be re-opened by the end of the workday on Friday, August 23 barring  any  unanticipated  problems. Traffic is  advised to plan an alternate route to avoid possible delays. No vehicles will be able to pass.

Any questions concerning this notice may be directed to the City Service Complex during normal business hours, Monday thru Friday from 7:00 AM to 3:30 PM at 419-755-9806.

,

All About Richland

ODOT Road Project Update: Week Of August 18

17 Aug , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of August 18. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of August 11

11 Aug , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of August 11. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of August 4

3 Aug , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of August 4. It shows ongoing work as well as updates and new projects. Read More

, ,

All About Richland

ODOT Road Project Update: Week Of July 28

27 Jul , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of July 28. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of July 21

20 Jul , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of July 21. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of July 14

14 Jul , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of July 14. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of July 7

6 Jul , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of June 23. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of June 30

29 Jun , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of June 23. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update: Week Of June 23

24 Jun , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of June 23. It shows ongoing work as well as updates and new projects in both Crawford and Richland Counties. Read More

,

All About Richland

ODOT Road Project Update: Week Of June 16

15 Jun , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of June 16. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

Section Of Millsboro Road To Close For Ninety Days

14 Jun , 2019  

On Thursday, the Richland County Engineer’s Office shared news of an upcoming road closure and a revised schedule for a second closed road. First, Millsboro Road, between Lexington-Springmill Road and Home Road in Springfield Township, will be closed starting Monday, June 17, and will remain closed for ninety (90) days. Read More

,

All About Richland

ODOT Road Project Update: Week Of June 9

8 Jun , 2019  

Each week through the end of construction season, we will be sharing the latest road project update from District Three of the Ohio Department of Transportation for work in Ashland, Crawford, and Richland Counties. This is the project report for work taking place during the week of June 9. It shows ongoing work as well as updates and new projects. Read More

,

All About Richland

ODOT Road Project Update #2

4 Jun , 2019  

NOTE: As of Sunday evening, ODOT District Three had not shared the regular weekly project update for the week beginning June 2. We re-posted last week's list over the weekend; on Monday afternoon, the current list was published and can be found below. Read More

,