ASHLAND COUNTY
State Route 3 resurfacing project – State Route 3, from the village of Loudonville to the city of Wooster, will be reduced to one lane of traffic for a resurfacing project. Traffic will be maintained by flaggers. Estimated completion: September
State Route 3 resurfacing project – State Route 3, from the Knox County line to state Route 39, will have single lane closures for a resurfacing project. Crews will start replacing curb ramps in the village of Loudonville. Traffic will be maintained by flaggers. Estimated completion: October
U.S. Route 42 bridge replacement – U.S. 42, between Cleveland Avenue and Township Road 793, will have single lane closures for a bridge replacement project.
NEW IMPACTS
On Thursday, July 30 the road will be closed between U.S. 250 and Township Road 793 so the box beams for the bridge can be set. This is a single day closure. The road is scheduled to reopen the same day and traffic will resume to its normal single lane configuration for the duration of the project. The detour route for northbound motorists is U.S. 42 to U.S. 250, east on U.S. 250 to I-71, north on I-71 to Route 301, north on Route 301 to U.S. 41 and reverse for southbound motorists. Estimated completion: October
State Route 60 resurfacing project – State Route 60, from U.S. 30 to County Road 775, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers during working hours. Estimated completion: October
State Route 179 culvert replacement – State Route 179, just south of state Route 95, is closed for a culvert replacement. The detour route for southbound motorists will be state Route 179 to Route 95, west on Route 95 to Route 60, south on Route 60 to Route 3, northeast on Route 3 to Route 179, and reverse for northbound motorists. Estimated completion: Wednesday, August 19
State Route 179 resurfacing project – State Route 179, from the village of Hayesville to the Holmes County line, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers during working hours. Estimated completion: October
U.S. Route 250 resurfacing project – U.S. 250, from the village of Bailey Lakes to Westlake Drive, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers during working hours. Estimated completion: October
CRAWFORD COUNTY
State Route 4 bridge repairs – State Route 4, between state Route 103 west and Washington Street/Clady Road, is closed for a bridge repair project. The detour route for northbound motorists will be state Route 4 to Route 103, west on Route 103 to Route 19, north on Route 19 to U.S. 224, east on U.S. 224 to Route 4 and reverse for southbound motorists. Estimated completion: Friday, August 7
State Route 19 resurfacing project – State Route 19, from Evans Avenue to the city of Bucyrus corporation limits, will be reduced to one lane of traffic for a resurfacing project. Traffic will be maintained by flaggers. Estimated completion: Later this month
U.S. Route 30 bridge sealing and structure work – U.S. 30 eastbound and westbound, from just east of State Route 98 to Old Lincoln Way, will have single lane closures for concrete sealing and striping. Estimated completion: August
State Route 97 resurfacing project – State Route 97, between Millsboro Road to the Morrow County line, will be reduced to one lane for a resurfacing project. Traffic will be maintained by flaggers. Estimated completion: Later this month
RICHLAND COUNTY
State Route 13 bridge repairs – State Route 13, at the bridge between Ogle Street and state Route 97, will have daytime single lane closures as needed for bridge painting. The overhead clearance will be reduced to 14’ 6”. Traffic will be maintained by traffic control signals. Estimated completion: August
U.S Route 30 major rehabilitation – U.S. 30, from state Route 309 to just east of the 5th Avenue ramps, will have single lane closures for a major rehabilitation project. Traffic will always be maintained.
NEW IMPACTS
CONTINUING IMPACTS
Estimated completion: May 2023
U.S. Route 30 minor rehabilitation – U.S. 30 eastbound and westbound, from the W. 4th Street interchange to just west of the Lexington-Springmill interchange, will have daily/nightly lane closures in order to complete pavement repairs, milling, paving, striping, berming, and guardrail work. One 11’ lane of traffic will be maintained in each direction at all times. Estimated completion: August
U.S. Route 42 resurfacing project – U.S. 42, from Fox Road to the city of Mansfield corporation limit, will have single lane closures for a resurfacing project. Traffic will be maintained by periodic flagging operations as needed. Estimated completion: Later this month
Interstate 71 resurfacing project – I-71 northbound and southbound, from the Morrow county line to state Route 97, will have single lane, daytime closures and double lane, nighttime closures for a resurfacing project.
NEW IMPACTS
The state Route 13 northbound exit ramp will close Wednesday, July 29 for 10 days to complete pavement repairs.
CONTINUING IMPACTS
Crews continue night work on I-71 from the Morrow/Richland county line to the state Route 13 exit. Work will progress in both zones simultaneously. Estimated completion: October
State Route 95 culvert replacement – State Route 95, just south of Ramsey Road, will close Monday, July 27 for a culvert replacement. The detour route for northbound motorists is state Route 95 to Route 97, east on Route 97 to Route 3, north on Route 3 to Route 39, northwest on Route 39 to Route 95, and reverse for southbound motorists. Estimated completion: Friday, August 7
State Route 309 minor rehabilitation – State Route 309, from state Route 314 to Home Road, will have single lane closures for a resurfacing project. Traffic will be shifted over into 10’ lanes and will be divided by portable barrier wall in each direction. Estimated completion: September