As Ohioans gear up for another year of road improvements, the Ohio Department of Transportation (ODOT) has released its 2025 Construction Guide, detailing the ambitious plans to enhance the state’s transportation network. With a record-breaking investment and a focus on safety, the 2025 season is set to bring transformative changes to roads and bridges across Ohio.
Fourteen Richland County projects are included in the Guide and are profiled below. ODOT District 3-wide initiatives will be reviewed in a separate post.
ODOT has committed an unprecedented $2.8 billion to fund over 900 projects in the upcoming construction season. This significant investment underscores the state’s dedication to improving roadways, reducing congestion, and ensuring safer travel for millions of Ohioans. The extensive improvements scheduled for 2025 include more than 5,600 miles of road resurfacing and repairs, as well as 885 bridges set for maintenance, upgrades, or full replacements.
Major Projects and Safety Initiatives
Among the extensive list of projects, 39 new “major” undertakings—each valued at over $10 million—are set to make a lasting impact. These large-scale projects will address critical infrastructure needs, from highway expansions to essential bridge rehabilitations. In addition, ODOT has allocated resources to 176 safety-focused projects, aiming to improve road conditions, enhance visibility, and implement modern traffic management systems to reduce serious and fatal crashes.
What This Means for Drivers
With such a vast scope of projects, Ohio drivers should prepare for construction zones, detours, and adjusted traffic patterns throughout the year. However, ODOT is committed to minimizing disruptions and ensuring a smooth transition as improvements take shape. To explore the full scope of the 2025 Construction Guide, including project maps, timelines, and traffic impact details, visit ODOT’s official website. Stay informed, stay patient, and get ready for a safer, smoother driving experience across the Buckeye State.
Project ID | County | Project Name | Description | Traffic Impact | District | Start Date | End Date | Cost |
---|---|---|---|---|---|---|---|---|
107727 | Richland | SR 39 & SR 61 Culvert Repairs | Culvert repairs at SR 39 just south of Leppo Rd and SR 61 just north of Graham Rd. | Traffic maintained at all times. | District 03 | 2025-05-01 | 2025-06-30 | $462,000 |
107970 | Richland | SR 545 Major Rehabilitation | Complete pavement replacement with buggy lanes. | Traffic maintained at all times. | District 03 | 2025-11-07 | 2026-10-30 | $21,430,000 |
112404 | Richland | Main St Upgrades in Mansfield | Intersection improvements, pedestrian safety upgrades, and landscaping. | Traffic maintained at all times. | District 03 | 2025-04-01 | 2026-10-31 | $15,853,000 |
113284 | Richland | U.S. 42 & SR 545 Culvert Replacements | Culvert replacements with 30-day detours. | 30 day detour for each location. | District 03 | 2025-06-02 | 2025-09-30 | $491,000 |
113325 | Richland | SR 13 Major Rehabilitation | Major resurfacing along SR 13. | Traffic maintained at all times. | District 03 | 2024-07-31 | 2027-05-14 | $18,484,000 |
115001 | Richland | U.S. 42 Traffic Signal Upgrades | Traffic signal upgrades at multiple intersections. | Traffic maintained at all times. | District 03 | 2025-04-01 | 2026-04-01 | $1,126,000 |
115032 | Richland | SR 314 Culvert Replacement | Culvert replacement with a 30-day detour. | 30 day detour | District 03 | 2025-04-01 | 2025-06-01 | $442,000 |
116058 | Richland | Coursen Rd (TR 128) Bridge Replacement | Complete bridge replacement with 120-day detour. | 120 day detour | District 03 | 2025-05-01 | 2025-10-01 | $1,184,000 |
116657 | Richland | I-71 Resurfacing | Resurfacing from SR 13 to Ashland County line. | Traffic maintained at all times. | District 03 | 2026-06-01 | 2026-12-31 | $10,605,000 |
118245 | Richland | Millsboro Trail in Mansfield | Construction of a multiuse trail. | Traffic maintained at all times. | District 03 | 2025-06-01 | 2025-10-31 | $897,000 |
119003 | Richland | Townline Rd (TR 79) Bridge Replacement | Bridge replacement with 90-day detour. | 90 day detour | District 03 | 2025-05-01 | 2025-10-31 | $560,000 |
119146 | Richland | Trimble Rd Trail Extension | Multiuse trail to connect the B&O Trail. | Traffic maintained at all times. | District 03 | 2025-07-01 | 2025-10-31 | $2,073,000 |
119727 | Richland | I-71 Geologic Maintenance | Slope stabilization along I-71. | Traffic maintained at all times. | District 03 | 2025-06-30 | 2025-10-31 | $1,485,000 |
121720 | Richland | SR 13, SR 95 & SR 97 Resurfacing | Resurfacing along multiple segments. | Traffic maintained at all times. | District 03 | 2026-05-01 | 2026-08-31 | $5,738,000 |