By 1812Blockhouse, Ohio Department of Transportation

The Ohio Department of Transportation (ODOT) is kicking off the 2022 construction season throughout the state, with more than 130 projects worth nearly $800 million planned in the central Ohio area this year. This includes 42 pavement improvement projects, 22 bridge projects, and 31 projects aimed directly at improving safety on Ohio’s roads.

North Central Ohio will be a hub of activity as numerous projects get underway. These include regional projects with a local component as well as four major county transportation projects. Each major project is profiled below.

“Safety has been the top priority since the first day of the DeWine Administration. We’re constantly looking for ways to better engineer our roads to ensure they’re as safe as possible for those who use them each day,” said ODOT Director Jack Marchbanks. “However, drivers have an important role to play too. We need every motorist to buckle up, obey the speed limit, drive sober, and drop the distractions.”

In terms of Columbus work, safety is also a major component of the work beginning at Interstates 70/270 and Brice Road this year, the first phase of the Far East Freeway major reconstruction project. This series of projects will address the growing regional travel demand by improving safety at various interchanges along the I-70 corridor from U.S. Route 33 to State Route 256.

“This project is the first step towards easier travel on the east side,” said Interim District 6 Deputy Director Toni Turowski. “This corridor is key for the Columbus metro area and critical for through traffic to connect to eastern Ohio and beyond.”

Expected to begin this summer, the initial phase will replace the existing loop ramp from I-270 south to I-70 east with a flyover ramp to reduce weaving and merging at the interchange. It will also add an eastbound lane between I-270 and Brice Rd. and reconfigure ramps from I-270 north to I-70 east and Brice Rd. to address congestion and improve safety.

In addition to a number of maintenance and standard repair projects taking place in 2022, here is a list of major ODOT projects scheduled for Ashland, Crawford, and Richland Counties:

ASHLAND

U.S. ROUTE 30 AND STATE ROUTE 603 INTERSECTION IMPROVEMENT – Converting the intersection into a Reduced Conflict U-Turn (RCUT) 

Begin Date: August 2021

Estimated End: August 2022

Project Cost: $3.1 million

Traffic Impacts: Lane closures on U.S. 30 and a 60 day closure of SR 603 for both approaches to U.S. 30

U.S. ROUTE 250 AND STATE ROUTE 89 INTERSECTION IMPROVEMENT – Improve intersection’s sight distance by lowering the crest vertical curve to the west of the intersection and widen the radii at the intersection to accommodate heavy truck volumes

Estimated Begin: May 2022

Estimated End: September 2022

Project Cost: $1.7 million 

Traffic Impacts: 90 day closure of U.S. 250

U.S. ROUTE 250 AND STATE ROUTE 13 BRIDGE REPLACEMENTS – U.S. 250, just west of Township Rd 35 and SR 13, just south of U.S. 224

Estimated Begin: May 2022

Estimated End: November 2022

Project Cost: $455,000 

Traffic Impacts: U.S. 250 30 day detour/ SR 13 45 day detour

U.S. ROUTE 250/ STATE ROUTE 60 / FAULTLESS DR. ROUNDABOUT – Converting a two way stop controlled intersection into a single-lane roundabout in the city of Ashland

Estimated Begin: May 2022

Estimated End: September 2022

Project Cost: $1.7 million

Traffic Impacts: 90 day closure of SR 60 and Faultess Dr. 

U.S. ROUTE 42 SLIDE REPAIR – Just east of Twp. Rd. 101

Estimated Begin: April 2023

Estimated End: July 2023

Project Cost: $250,000

Traffic Impacts: Traffic will be maintained

STATE ROUTE 95/STATE ROUTE 603 CHIP SEAL – SR 95 from SR 39 to SR 60 in Ashland County and SR 603 from SR 39 to SR 95 in Richland County

Estimated Begin: June 2022

Estimated End: September 2022

Project Cost: $755,000

Traffic Impacts: Traffic will be maintained

CRAWFORD

STATE ROUTE 598 SAFETY IMPROVEMENT – Safety improvement project including widening and the addition of a turn lane on SR 598 from Carter Dr. to Brandt Rd. in the city of Galion – Begin Date: September 2021

Estimated End: October 2022

Project Cost: $3.6 million 

Traffic Impacts: Traffic will be maintained 

STATE ROUTE 96 CULVERT REPLACEMENT – Two culvert Replacements both just east of SR 602

Estimated Begin: September 2022

Estimated End: October 2022 Project Cost: $210,000

Traffic Impacts: 120 day closure

U.S. ROUTE 30 RESURFACING – From just east of SR 602 to just east of SR 61 Estimated Begin: April 2022

Estimated End: September 2022

Project Cost: $6.6 million

Traffic Impacts: Traffic will be maintained 

STATE ROUTE 602 MAJOR REHABILITATION – Full depth replacement of SR 602 from Old Lincoln Way to Guiss Rd.

Estimated Begin: May 15, 2022

Estimated End: October 2022

Project Cost: $8.6 Million

Traffic Impacts: Traffic will be maintained

STATE ROUTE 96 REHABILITATION = Full depth rehabilitation from SR 98 to SR 602

Estimated Begin: April 2023

Estimated End: October 2023

Project Cost: $2.7 Million

Traffic Impacts: Traffic will be maintained

STATE ROUTE 39 MINOR REHABILITATION – From the southern village limits of Tiro to the western city limits of Shelby and SR 96 from the RIC Co. line to SR 39

Estimated Begin: April 2023

Estimated End: June 2023

Project Cost: $2 Million

Impacts: Traffic will be maintained

RICHLAND

U.S. ROUTE 30 MAJOR REHABILITATION – From SR 309 to just east of the Fifth Ave. ramps

Estimated Begin: May 2020

Estimated End: May 2023 

Project Cost: $61 Million

Traffic Impacts: Traffic will be maintained

U.S. ROUTE 42 CULVERT PRESERVATION – Two structures both just north of W. Hanley Rd.

Estimated Begin: June 2022

Estimated End: October 2022

Project Cost: $350,000.00

Traffic Impacts: Traffic will be maintained

I-71 PREVENTATIVE MAINTENANCE – From the SR 13 structure to just south of Washington Rd.

Estimated Begin: August 2022

Estimated End: October 2022

Project Cost: $375,000.00

Traffic Impacts: Traffic will be maintained

STATE ROUTE 314 SIGNAL REPLACEMENT – At the intersection of SR 314 and Fourth Street

Estimated Begin: June 2022

Estimated End: April 2023

Project Cost: $200,000.00 

Traffic Impacts: Traffic will be maintained

STATE ROUTE 39 MINOR REHABILITATION – From just north of the I-71 interchange to SR 603

Estimated Begin: August 2022

Estimated End: November 2022

Project Cost: $2.6 Million

Traffic Impacts: Traffic will be maintained

U.S. ROUTE 30 MINOR REHABILITATION – From the Fifth Ave Interchange ramps to just past the Ashland County Line’

Estimated Begin: January 2023

Estimated End: December 2023

Project Cost: $8.2 Million

Traffic Impacts: Traffic will be maintained

STATE ROUTE 39 BRIDGE REPLACEMENT – Between E 6 St. and Lafayette Ave. in the city of Mansfield

Estimated Begin: April 2022

Estimated End: August 2022

Project Cost: $994,303.00

Traffic Impacts: 120 day closure

STATE ROUTE 96 BRIDGE REPLACEMENT – Just east of SR 603

Estimated Begin: April 2023

Estimated End: November 2023

Project Cost: $2.3 Million

Traffic Impacts: 120 day closure 

“It’s so important for drivers to focus on the road when they’re behind the wheel – especially when projects like these are underway,” said Turowski. “Construction often means new traffic patterns, narrower lanes, and lower speed limits. Staying alert in work zones is imperative to keeping workers and other drivers safe.”

You May Also Like

Fiber Enthusiasts Unite: Autumn Fiber Festival Returns To Mansfield In October

The festival showcases a wide variety of fiber arts.

Richland County Population Holding Steady

By 1812Blockhouse When the US Census Bureau released its latest estimates last…

Local Court Awarded Technology Grant

The Mansfield Municipal Court has been awarded a technology grant, Court News…

Patient Credits OhioHealth Mansfield Hospital Unit With Miraculous Recovery

It was a long road to recovery for Mullins.