Spring driving in Ohio brings a familiar sight: orange barrels lining highways and crews returning to work. In 2026, that seasonal rhythm arrives with a record-setting investment, as the Ohio Department of Transportation begins a $3.4 billion construction season statewide.
The scope is significant. A total of 977 projects are scheduled, including improvements to 739 bridges and approximately 4,562 miles of roadway. To put that in perspective, that distance is roughly equivalent to driving from Columbus to San Diego and back. Projects are included in Ashland, Crawford, and Richland Counties, and are profiled below. We will include a list of projects across ODOT District 3 on Monday.
Much of the focus remains on maintaining what already exists. ODOT reports that 80 cents of every dollar invested this year will go toward preserving current roads and bridges. In addition, 36 major projects each carry a price tag exceeding $10 million. Safety continues to be a central priority. The 2026 construction season includes the launch of 174 safety-focused projects, reinforcing Ohio’s position as a national leader in per capita roadway safety investment.
“As a state that makes and moves things, we must have a safe transportation system that is well maintained,” said Governor DeWine. “As they do each year, our ODOT teams will be making enhancements to Ohio’s roadways to better protect everyone traveling on them.”
Since 2019, the DeWine administration has directed $15.5 billion into 6,067 transportation projects across Ohio.
“This record-setting construction season is a testament to ODOT’s focus on building a more resilient transportation system and saving lives,” said Pamela Boratyn, ODOT Director. “This investment positions Ohio as the heart of the nation’s supply chain and continues to fuel the state’s economic engine.”
Work Zone Safety Remains a Concern
Alongside the construction activity comes a renewed warning about work zone safety.
According to the Ohio State Highway Patrol, there were 4,435 work zone crashes in Ohio last year. Of those, 34 percent occurred with workers present. The consequences remain serious. Seventeen fatal crashes claimed 21 lives, while another 96 crashes resulted in serious injuries. Speeding and following too closely continue to be the leading causes. Troopers issued 7,019 speeding citations in work zones, with more than a third involving drivers traveling over 20 miles per hour above the posted limit.
The risks were underscored by a recent tragedy in Columbus. On February 28, a vehicle entered a closed section of I-70 and struck 25-year-old construction worker Jordan Thomas, an employee of Kokosing Construction. He later died from his injuries. The driver fled the scene and has not been identified.
Authorities are offering a $110,000 reward for information leading to an arrest. Anyone with information is asked to contact Central Ohio Crime Stoppers at 614-461-8477. Tips can be submitted anonymously.
ASHLAND, CRAWFORD, AND RICHLAND COUNTY PROJECTS
| Project | Traffic Impact | Start | End | Value |
|---|---|---|---|---|
|
Mohican Covered Bridge Deck Resurfacing ODNR resurfacing of covered bridge deck near Pheasant Hill Trail. |
30-day detour | Mar 2026 | Apr 2026 | $283K |
|
SR 511 Resurfacing Pavement work from north of CR 500 to Lorain County line. |
Traffic maintained | May 2026 | Oct 2026 | $2.36M |
|
SR 60 Culvert Replacement Culvert replacement between TR 1600 and CR 1775. |
30-day detour | May 2026 | Oct 2026 | $489K |
|
U.S. 250 Resurfacing Resurface from CR 1575 to Camp Road at Wayne County line. |
Traffic maintained | Aug 2026 | Sep 2026 | $3.81M |
|
SR 60, 302 & 511 Resurfacing Multi-route resurfacing across Ashland County corridors. |
Traffic maintained | May 2027 | Sep 2027 | $6.85M |
|
I-71 Resurfacing (Ashland) Resurface from Richland County line to north of U.S. 250. |
Traffic maintained | Apr 2027 | Sep 2027 | $14.36M |
|
SR 545 Reconstruction Full-depth reconstruction from Olivesburg to Savannah with buggy lanes. |
Traffic maintained | Jan 2027 | Oct 2027 | $19.48M |
|
SR 39 Bridge Replacement Replace bridge between CR 917 and TR 857. |
90-day detour | Jul 2026 | Oct 2026 | $443K |
|
U.S. 30 Bridge Replacement Replace east and westbound bridges near SR 98. |
Traffic maintained | Apr 2026 | Aug 2027 | $7.64M |
|
SR 4 & SR 96 Resurfacing Resurfacing in Crawford County corridors to Huron and Richland lines. |
Traffic maintained | May 2026 | Oct 2026 | $1.49M |
|
SR 19 Resurfacing (Bucyrus–Galion) Includes additional resurfacing work in Wayne County. |
Traffic maintained | Aug 2026 | Jul 2027 | $2.57M |
|
SR 100 Bridge Replacement Replace bridge west of SR 19/Carey Road intersection. |
60-day detour | Apr 2027 | Oct 2027 | $770K |
|
SR 13, 95 & 97 Resurfacing Multi-route resurfacing including Butler area corridors. |
Traffic maintained | May 2026 | Oct 2026 | $5.27M |
|
I-71 Resurfacing (Richland) Resurface from SR 13 to Ashland County line. |
Traffic maintained | Apr 2026 | Oct 2026 | $10.02M |
|
U.S. 42 Culvert Replacements (Hanley Rd) Culvert work with detour on Hanley Road. |
Traffic maintained; detour on Hanley Rd | Aug 2026 | Oct 2026 | $307K |
|
U.S. 30 Bridge Repairs (Reed Rd) Repair bridge damaged in accident. |
Traffic maintained | Jul 2026 | Oct 2026 | $861K |
|
U.S. 42 Culvert Replacement Replace culvert between Cedarwood Dr. and Gables Blvd. |
30-day detour | Aug 2026 | Sep 2026 | $255K |
|
I-71 & SR 226 Culvert Repairs Repairs north of U.S. 30 and in Wayne County. |
Traffic maintained; ramp detour | Apr 2027 | Nov 2027 | $789K |
|
Elm Street Bridge Replacement (Butler) Replace bridge west of Grant Street. |
90-day detour | Aug 2026 | Oct 2026 | $1.07M |
|
Richland B&O Trail Resurfacing Resurface multi-use path from Butler to Mansfield. |
Traffic maintained | Oct 2026 | Dec 2026 | $1.53M |
|
SR 13 Bridge Replacement Replace bridge between Lattimer Rd and Adario West Rd. |
45-day detour | Apr 2027 | Nov 2027 | $633K |
|
SR 39 Culvert Replacement Culvert replacement west of SR 603. |
30-day detour | Apr 2027 | Oct 2027 | $165K |
|
SR 314 & SR 545 Resurfacing Resurface corridors from Morrow County line and within Mansfield area. |
Traffic maintained | May 2027 | Sep 2027 | $6.15M |